Dixon CA 45-day data center and BESS moratorium

Dixon, California — City Council Unanimously Adopts a 45-Day Moratorium on New Data Center and Battery Storage Applications (Sept. 30, 2026)
Dixon, CA · Dixon, CA, 45-day data center/BESS moratorium (Sept. 30, 2026)

Status
In effect
Took effect
September 30, 2026
Applies to
Data center and battery storage developers seeking land-use approvals in Dixon, CA
Enforced by
City of Dixon City Council; Community Development

The Dixon, California City Council voted unanimously at a special meeting on Sept. 30, 2026 to pause approval of new land-use applications for data centers and battery energy storage systems for 45 days. The pause covers data centers of at least 5,000 square feet or 2 megawatts. No such projects are proposed in Dixon, and council members said the pause will likely be extended while the city studies the issue.

Who is protected: Dixon, CA residents

Legal detail

Dixon (Solano County) City Council special meeting Wed. Sept. 30, 2026: unanimous 45-day moratorium on new land-use applications for data centers (>=5,000 sq ft or >=2 MW, plus associated on-site energy infrastructure) and battery energy storage systems. No data center or BESS projects currently proposed in Dixon. Options after study: added permitting, environmental review, or prohibition. NOT ESTABLISHED: ordinance number; whether adopted as an urgency ordinance under Gov. Code 65858; exact expiry date.

Key facts

JurisdictionDixon, CA
LevelCity / local
StrengthModerate
EnactedSeptember 30, 2026
CitationDixon, CA, 45-day data center/BESS moratorium (Sept. 30, 2026)
Private right of actionNo, agency enforcement only
Topicsdata-center siting and energy
News reportDixon council puts data centers, BESS applications on hold — Daily Republic (Oct. 2, 2026)