Imperial Irrigation District (CA) — Board Adopts Large Load Tariff for Customers Above 20 MW: Infrastructure Cost Recovery, 85% Minimum Charge, Deposits, and Curtail-First Rule (Sept. 15, 2026)
Imperial Irrigation District (Imperial County), CA · Imperial Irrigation District Board, Large Load tariff/rules (approved Sept. 15, 2026)

Status
Enacted (not yet in effect)
Applies to
Large-load customers above 20 MW in IID territory, mainly data centers
Enforced by
Imperial Irrigation District

The Imperial Irrigation District, the public power utility for the Imperial Valley, approved new pricing rules for very large electricity users such as data centers (more than 20 megawatts). These customers must pay for the substations, lines and other upgrades they need. They must pay a monthly minimum of at least 85% of their contracted energy use, put down cash deposits, sign 15-year commitments, and meet renewable energy requirements. When demand spikes, IID can cut their power first. The aim is to keep ordinary ratepayers from covering data-center costs.

Who is protected: IID electric ratepayers in the Imperial Valley (and parts of Riverside County), shielded from paying for large-load infrastructure and stranded costs

Legal detail

IID Board of Directors, unanimous vote, Tuesday Sept. 15, 2026 (KPBS article published Sept. 16): large-load rules for customers above 20 MW. Terms per KPBS: (1) the customer pays for infrastructure upgrades (substations, distribution, transmission); (2) a minimum monthly charge of at least 85% of contracted energy usage, with no fixed dollar figure; (3) a 15-year service commitment; (4) a cash deposit; (5) renewable procurement obligations; (6) IID may curtail these customers first when demand surges. Context: Sebastian Rucci's proposed data center complex in the City of Imperial (see Imperial CA Data Center Moratorium and the Imperial County litigation entries). The effective date was not reported. IID is a special district (irrigation and power), entered at county level with _body_type utility.

Key facts

JurisdictionImperial Irrigation District (Imperial County), CA
LevelCounty
StrengthModerate
EnactedSeptember 15, 2026
CitationImperial Irrigation District Board, Large Load tariff/rules (approved Sept. 15, 2026)
Private right of actionNo, agency enforcement only
PenaltiesMinimum charges, deposits and first-in-line curtailment under tariff terms
Topicsdata-center siting and energy · consumer protection
News reportImperial Valley utility adopts new pricing rules, putting data centers first for power cuts — KPBS

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.