Richmond CA 45-day data center moratorium (2026)
Richmond, California — City Council Approves a 45-Day Moratorium on New Data Centers, the Opening Interval of a California Interim Urgency Ordinance, on the Same Night Neighbouring Hayward Directed Staff to Return With Moratorium Options (September 2026)
Richmond, CA · Richmond, Cal. — 45-day interim moratorium on new data centers, approved September 15, 2026
- Status
- In effect
- Expires
- October 30, 2026
- Applies to
- Data center developers seeking new approvals in Richmond during the moratorium
- Enforced by
- Richmond City Council; city planning department
The Richmond City Council approved a 45-day moratorium on new data centers on Tuesday, September 15, 2026. The 45-day figure is not arbitrary: California Government Code section 65858 lets a city adopt an interim urgency ordinance freezing land uses for 45 days by a four-fifths vote, then extend it once for 10 months and 15 days, and once more for a year — a maximum of two years. Almost every California pause in this dataset starts at exactly 45 days for this reason, and the real question for any of them is whether the council comes back and extends. Richmond's adoption came the same night the Hayward City Council directed staff to return with options for its own data center moratorium, and while more than 70 speakers were registering opposition to data centers at the Oakland City Council — evidence of a co-ordinated East Bay wave rather than three unrelated local decisions.
Who is protected: Richmond residents in Contra Costa County, California
Legal detail
Richmond, Calif. (Contra Costa County) — 45-DAY MORATORIUM ON NEW DATA CENTERS approved by the City Council on TUESDAY, SEPTEMBER 15, 2026. THE 45-DAY TERM IDENTIFIES THE INSTRUMENT: Cal. Gov. Code § 65858 authorises an interim urgency ordinance prohibiting uses in conflict with a contemplated zoning proposal, adopted by a FOUR-FIFTHS VOTE, effective for 45 DAYS, extendable once by 10 MONTHS AND 15 DAYS and once more by 1 YEAR (two years maximum aggregate), with each extension requiring notice, hearing and a written report on measures taken to alleviate the condition. Cohort: Gilroy CA interim urgency data center moratorium (2026) (45-day, unanimous, September 14 2026), Palm Springs Data Center Moratorium (2026). expires_date 2026-10-30 IS COMPUTED as 45 days from adoption and IS NOT STATED IN THE SOURCE. EAST BAY CLUSTER, SAME NIGHT: the source reports that on the same Tuesday the HAYWARD CITY COUNCIL DIRECTED STAFF TO RETURN WITH OPTIONS for a data center moratorium (unindexed lead, deferred in the triage ledger — direction to staff is not an adopted measure), while more than 70 speakers addressed the OAKLAND City Council in opposition even though data centers were not on that day's agenda (Oakland CA 45-day data center moratorium (Oct. 2026) is already indexed; Oakland Councilmember CARROLL FIFE is proposing an urgency ordinance imposing a temporary moratorium on city approval of land-use entitlements or agreements for data centers, to receive its first formal airing at the council's Life Enrichment Committee). NAMING CAUTION RECORDED DELIBERATELY: the source headline reads 'Following Richmond, Hayward, Fife seeks pause' — 'Fife' THERE IS OAKLAND COUNCILMEMBER CARROLL FIFE, NOT THE CITY OF FIFE, WASHINGTON. No Fife WA measure is asserted by this source and none should be inferred from it. SOURCE LIMIT: the reporting sentence is CUT MID-CLAUSE BY A PAYWALL ('the Richmond City Council approved a 45-day moratorium on new data centers,') so any scope qualifiers, exemptions, vote tally and ordinance number that followed WERE NOT CAPTURED.
Key facts
| Jurisdiction | Richmond, CA |
|---|---|
| Level | City / local |
| Strength | Moderate |
| Enacted | September 15, 2026 |
| Citation | Richmond, Cal. — 45-day interim moratorium on new data centers, approved September 15, 2026 |
| Private right of action | No, agency enforcement only |
| Penalties | New data center applications may not be approved during the moratorium period |
| Topics | data-center siting and energy · consumer protection · government use of AI |
| News report | Richmond City Council approves 45-day moratorium on new data centers — Richmond Standard, Sept. 16, 2026 |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.