Chandler Data Center Noise Ordinance

Chandler, AZ Data Center Zoning Ordinance No. 5033 (Noise and Siting Standards)
Chandler, AZ · City of Chandler, Ariz., Ord. No. 5033 (eff. Jan. 5, 2023)

Status
In effect
Took effect
January 5, 2023
Applies to
Operators and developers of primary-use data centers in Chandler
Enforced by
City of Chandler Development Services / Planning Division

Responding to resident complaints about constant noise from cooling equipment and crypto-mining operations, Chandler unanimously adopted zoning rules governing where and how data centers operate. New primary-use data centers are permitted only in Planned Area Development zones and must do baseline sound studies, keep operational noise below that baseline, repeat noise studies annually for five years, notify nearby residents, and limit backup-generator testing to weekday business hours.

Who is protected: Residents near data center and crypto-mining facilities in Chandler

Legal detail

City of Chandler Ordinance No. 5033 (PLH22-0053, adopted Dec. 5, 2022; eff. Jan. 5, 2023) defines data centers, restricts them to PAD zoning, and imposes noise-baseline, annual sound-study, resident-notification, and generator-testing requirements.

Key facts

JurisdictionChandler, AZ
LevelCity / local
StrengthModerate
EnactedDecember 5, 2022
CitationCity of Chandler, Ariz., Ord. No. 5033 (eff. Jan. 5, 2023)
PenaltiesZoning code enforcement
Topicsdata-center siting and energy
Agency pageChandler's data center ordinance now in effect | City of Chandler