Rio Grande County CO hyperscale data center prohibition (2026)

Rio Grande County, Colorado — Commissioners Adopt a Resolution PROHIBITING Any Large-Scale or Hyperscale Data Centers in the County, Choosing a Size-Defined Prohibition Over a Pause (August 2026)
Rio Grande County, CO · Rio Grande County, Colo. — commissioners' resolution prohibiting large-scale or hyperscale data centers (2026)

Status
In effect
Took effect
August 8, 2026
Applies to
Developers of large-scale or hyperscale data centers, which may not be sited in Rio Grande County
Enforced by
Rio Grande County Board of County Commissioners; county land use administration

Rio Grande County's commissioners adopted a RESOLUTION PROHIBITING ANY LARGE-SCALE, OR HYPERSCALE, DATA CENTERS IN THE COUNTY. This is a prohibition, not a pause, and the distinction matters: the county did not buy time to write rules, it decided the question. What makes the drafting interesting is that the prohibition is SIZE-DEFINED rather than use-defined. Rio Grande County has not barred data centers; it has barred large ones. That threads a needle several other jurisdictions in this dataset have struggled with. A flat ban on 'data centers' risks catching the server room in a hospital or a bank — which is why Marysville, Kansas had to write an express exclusion for ordinary server rooms and incidental IT equipment into its ordinance. A ban on 'AI data centers', as Poway, California has attempted, invites an operator to recharacterise a facility as general-purpose colocation. Prohibiting by SCALE avoids both problems, because size is observable and not susceptible to relabelling. The weakness is the mirror image: 'large-scale' and 'hyperscale' are industry terms of art, not legal definitions, and unless the resolution fixes a number — square feet, megawatts, or acreage — the county has moved the definitional problem rather than solved it. Whether it does fix one is not established. Rio Grande County sits in Colorado's San Luis Valley, a water-scarce high-desert basin, and this dataset separately records Alamosa, in the same valley, adopting a one-year moratorium with some councillors pressing for a permanent ban.

Who is protected: Residents of Rio Grande County, Colorado, and San Luis Valley water users

Legal detail

Rio Grande County, Colo. (San Luis Valley) — RESOLUTION PROHIBITING ANY LARGE-SCALE OR HYPERSCALE DATA CENTERS adopted by the Board of County Commissioners, reported 2026-08-08. INSTRUMENT CLASS: this is a PROHIBITION, not a moratorium — the county resolved the question rather than pausing it. Cohort: Irwindale CA data center ban ordinance (2026), Monterey Park Data Center Ban (Measure NDC), Cumberland RI data center zoning prohibition, Ordinance 26-22 (2026), Edgewater FL AI data center ban (2026), Jersey City NJ data center ban in industrial zones (Ord. 26-057), Los Angeles County prohibition on data centers in unincorporated areas (2026). THE DEFINITIONAL STRUCTURE IS THE ANALYTICALLY USEFUL FEATURE AND IT IS SIZE-BASED, WHICH IS UNUSUAL AMONG THE PROHIBITIONS. The three approaches recorded in this dataset and their failure modes: (1) USE-BASED ('data centers') — over-inclusive absent an exclusion, which is why Marysville KS 12-month data center moratorium (2026) needed express language that the definition 'does not include ordinary server rooms or information-technology equipment incidental to the main use of a property'; (2) WORKLOAD-BASED ('AI data centers', Poway CA AI data center ban ordinance, first reading (2026)) — under-inclusive and defeasible, since an operator may characterise a facility as general-purpose colocation, and that entry flags the ordinance's own definition as unobtained and administrability as the critical open question; (3) SIZE-BASED (here) — resistant to both, because scale is observable and not susceptible to relabelling. THE SIZE-BASED APPROACH'S OWN WEAKNESS IS THAT 'LARGE-SCALE' AND 'HYPERSCALE' ARE INDUSTRY TERMS OF ART, NOT LEGAL DEFINITIONS. Unless the resolution fixes a measurable threshold — square footage, megawatts of peak demand, or acreage — the county has relocated the definitional problem rather than resolved it, and enforcement would turn on characterisation at the permitting stage. WHETHER THE RESOLUTION FIXES A THRESHOLD IS NOT ESTABLISHED BY THE SOURCE and is the most important open question on this entry. Compare Port Angeles WA six-month data center moratorium (2026), where Councilmember Drew Schwab argued for abandoning the definitional exercise entirely in favour of regulating the IMPACTS of large resource users — an approach that would express the same intent in megawatts and gallons rather than in a label. INSTRUMENT CAUTION: the measure is a RESOLUTION of the board of county commissioners, not reported as a zoning ordinance amendment. In Colorado, county land-use regulation runs through the county zoning resolution adopted under C.R.S. Title 30, Article 28, and a bare policy resolution not incorporated into that framework would be weaker than a zoning amendment. THE SOURCE DOES NOT SAY WHICH THIS IS. GEOGRAPHIC CONTEXT: the San Luis Valley is a high-desert closed basin with acute water-rights pressure and long-standing groundwater sustainability litigation and administration, which is material background to a hyperscale prohibition though the source does not state water as the rationale. Alamosa, in the same valley, adopted a unanimous one-year moratorium with councillors reportedly eager to ban data centers permanently (also in the unwritten queue). NOT ESTABLISHED: the vote, the exact date, the resolution number, any threshold, the stated rationale, and whether unincorporated areas only are covered.

Key facts

JurisdictionRio Grande County, CO
LevelCounty
StrengthStronger
EnactedAugust 8, 2026
CitationRio Grande County, Colo. — commissioners' resolution prohibiting large-scale or hyperscale data centers (2026)
Private right of actionNo, agency enforcement only
PenaltiesNot stated in the located source
Topicsdata-center siting and energy · consumer protection · government use of AI
News reportRio Grande commissioners say no, for now, to data center — Coyote Gulch

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.