Fauquier Vint Hill PCID Large-Building Special Exception Amendment
Fauquier County, VA · ZOA (March 2024) (2024-03-14)
- Status
- In effect
- Took effect
- March 14, 2024
- Applies to
- Data center developers seeking approvals in Fauquier County
- Enforced by
- Fauquier County government / planning
Requires Board special-exception approval for any building >50,000 sq ft in the Vint Hill PCID, effectively capturing all data centers.
Who is protected: Fauquier County residents and ratepayers
Legal detail
Requires Board special-exception approval for any building >50,000 sq ft in the Vint Hill PCID, effectively capturing all data centers. Citation: ZOA (March 2024).
Key facts
| Jurisdiction | Fauquier County, VA |
|---|---|
| Level | County |
| Strength | Moderate |
| Enacted | March 14, 2024 |
| Citation | ZOA (March 2024) (2024-03-14) |
| Topics | data-center siting and energy |
| Agency page | Fauquier Vint Hill PCID Large-Building Special Exception Amendment — source |
More AI rules in Fauquier County, VA
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.