HomeLegal DirectoryDeSoto County FL 1-year data center moratorium (DCIP exemption)

In effect Moderate protection

DeSoto County, FL — Board of County Commissioners 1-Year Data Center Moratorium (DCIP Exemption)

DeSoto County, FL · DeSoto County, FL Board of County Commissioners data center moratorium (adopted 4-0, July 29, 2026; one commissioner recused)

The DeSoto County, Florida Board of County Commissioners voted 4-0 on July 29, 2026 (with the fifth commissioner recused) to impose a one-year moratorium on acceptance, processing, review, and approval of all data center applications, running through approximately July 29, 2027. The vote came after months of intense public opposition to a massive proposed data center campus. The moratorium contains a significant exemption: it does NOT apply to rezoning applications tied to DCIP Group's existing project at a decommissioned power plant site, where DCIP had already received rezoning for 34 acres in March 2026 and had applied for over 800 additional acres as part of a planned 1,300-acre, 12-facility campus.

Technical detail

DeSoto County (FL) Board of County Commissioners 4-0 vote (fifth commissioner recused), July 29, 2026. One-year moratorium on acceptance, processing, review, and approval of data center applications countywide; expires approximately July 29, 2027. Key exemption: moratorium does not apply to rezoning applications related to DCIP Group's existing project at the decommissioned Payne Creek power plant site (34 acres rezoned March 2026; 800+ additional acres applied for; total planned: ~1,300 acres / 12+ facilities). Adopted after months of sustained public opposition. DeSoto County is in southwest-central Florida; county seat is Arcadia.

Who is protected: DeSoto County, FL residents

Who must comply: Data center developers seeking applications in DeSoto County, FL (DCIP Group's existing project is explicitly exempted)

Key facts

JurisdictionDeSoto County, FL
LevelCounty
StatusIn effect
Protection strengthModerate protection
Effective date2026-07-29
Enacted2026-07-29
CitationDeSoto County, FL Board of County Commissioners data center moratorium (adopted 4-0, July 29, 2026; one commissioner recused)
Enforced byDeSoto County Board of County Commissioners; DeSoto County Planning Department
Private right of actionNo — agency enforcement only
Topicsdata-center siting and energy
Last verified2026-08-02
Official sourceDeSoto approves data center moratorium, but controversial project can advance — WGCU Public Media ↗

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.