Rule Establishing Special Contract Terms for Large-Load Customers Over…

Georgia Public Service Commission (Georgia Power) — Rule Establishing Special Contract Terms for Large-Load Customers Over 100 MW
Georgia Public Service Commission (Georgia Power) · Rule Establishing Special Contract Terms for Large-Load Customers Over 100 MW

Status
In effect
Took effect
January 23, 2025
Applies to
Georgia Public Service Commission (Georgia Power)

The Georgia PSC unanimously approved a rule allowing Georgia Power to bill new customers using more than 100 MW under special terms, requiring them to cover transmission and distribution construction costs, permitting contracts up to 15 years, and mandating PSC review of each large-load contract.

Who is protected: People subject to this body's AI/surveillance systems.

Key facts

JurisdictionGeorgia Public Service Commission (Georgia Power)
LevelState
StrengthLimited
CitationRule Establishing Special Contract Terms for Large-Load Customers Over 100 MW
Topicsdata-center siting and energy · consumer protection · government use of AI · AI disclosure and transparency
News reportGeorgia PSC approves new billing rules for data centers and large load customers | DCD