Hubbard Township OH One-Year Moratorium on Data Centers
Hubbard Township, OH · Trustees resolution Feb 10, 2026 (2026-02-10)
- Status
- In effect
- Expires
- February 10, 2027
- Applies to
- Data center developers seeking approvals in Hubbard Township
- Enforced by
- Hubbard Township government / planning
2-1 trustee vote in response to 'Project Milo'; county planning commission asked to evaluate zoning text amendment.
Who is protected: Hubbard Township residents and ratepayers
Legal detail
2-1 trustee vote in response to 'Project Milo'; county planning commission asked to evaluate zoning text amendment. Citation: Trustees resolution Feb 10, 2026.
Key facts
| Jurisdiction | Hubbard Township, OH |
|---|---|
| Level | City / local |
| Strength | Moderate |
| Enacted | February 10, 2026 |
| Citation | Trustees resolution Feb 10, 2026 (2026-02-10) |
| Topics | data-center siting and energy |
| Agency page | Hubbard Township OH One-Year Moratorium on Data Centers — source |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.