Preservation of Community Well-Being Collective v. Village of Grayslake, T5 Data Centers and Alter Asset Management — Suit to Void Approvals for $18B Data Center Campus (filed July 31, 2026)
Grayslake, IL · Preservation of Community Well-Being Collective et al. v. Village of Grayslake et al. (Ill. Cir. Ct., filed July 31, 2026)

Status
Blocked / in litigation
Applies to
Village of Grayslake; T5 Data Centers; Alter Asset Management
Enforced by
Illinois circuit court (Lake County, presumed)

Residents sued Grayslake and the developers of a planned $18 billion, 472-acre, 18-building data center campus, saying village officials deliberated improperly behind closed doors and approved a use the zoning code does not allow. They want the court to cancel the approvals and the development agreement and block new permits.

Who is protected: Grayslake-area residents (if plaintiffs prevail)

Legal detail

Suit filed 2026-07-31 (court and case number not stated in source; presumably Lake County Circuit Court). Claims: Illinois Open Meetings Act violations (closed-door deliberations, private communications); Grayslake zoning code does not expressly permit data centers; 2024-2025 approvals violated due process. Relief: nullify prior approvals, enjoin issuance of new permits, cancel the village-T5 development agreement. Project: $18B, 472 acres in the Cornerstone business park, 18 buildings; early site work began 2025; T5 paused a wetland remediation permit application (~16 acres) in July 2026.

Key facts

JurisdictionGrayslake, IL
LevelCity / local
CitationPreservation of Community Well-Being Collective et al. v. Village of Grayslake et al. (Ill. Cir. Ct., filed July 31, 2026)
Private right of actionNo, agency enforcement only
PenaltiesRequested relief: voiding of approvals and development agreement; injunction
Topicsdata-center siting and energy · AI disclosure and transparency
News reportIllinois residents sue to stop $18B data center — The Cool Down via Yahoo News (citing Daily Herald)

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.