Leon County FL 18-month data center moratorium (voted July 14, 2026; hearings pending)

Leon County, FL 18-Month Data Center Moratorium (Pending Formalization)
Leon County, FL · Leon County, FL Board of County Commissioners vote, July 14, 2026, 18-month data center moratorium (public hearings pending)

Status
Proposed / pending
Applies to
Data center developers seeking approvals in Leon County, FL (once the ordinance is formalized)
Enforced by
Leon County, FL Development Support and Environmental Management; Board of County Commissioners

Leon County, Florida (home of Tallahassee) commissioners voted on July 14, 2026 in favor of an 18-month moratorium on data centers. The moratorium is not final yet: public radio station WFSU reports that two public hearings are still required before the ordinance is formally in place.

Who is protected: Leon County, FL residents

Legal detail

Leon County (FL) Board of County Commissioners vote July 14, 2026 supporting an 18-month data center moratorium. Formalization incomplete: WFSU reporting indicates two public hearings remain before the moratorium ordinance takes effect, so this is tracked as proposed rather than effective. If finalized on the reported terms, the 18-month term would run to approximately January 2028.

Key facts

JurisdictionLeon County, FL
LevelCounty
CitationLeon County, FL Board of County Commissioners vote, July 14, 2026, 18-month data center moratorium (public hearings pending)
PenaltiesPermit/application denial during moratorium (once formalized)
Topicsdata-center siting and energy
News reportLeon County commissioners approve 18-month data center moratorium — WCTV

Related data-center siting and energy rules elsewhere