Bradley County TN Project MidSpan data center zoning lawsuit

Bradley County, TN — Developer of 'Project MidSpan' Sues to Stop Enforcement of County Data Center Zoning Rules Requiring 3,000 Feet From Schools (October 2026)
Bradley County, TN · Bradley County, TN — Developer of 'Project MidSpan' Sues to Stop Enforcement of County Data Center Zoning Rules Requiring 3,000 Feet From Schools (October 2026)

Status
Blocked / in litigation
Applies to
Bradley County, TN; Project MidSpan developer
Enforced by
Bradley County, TN

A New York-based development group that bought about 306 acres near Walker Valley High School has sued Bradley County, Tennessee, asking a judge to stop the county from enforcing new data center zoning rules. The rules require data centers to be 3,000 feet from schools; the proposed Project MidSpan building would be 1,700 feet away. The county mayor told commissioners the county will fight the suit and pay legal costs from the general fund because insurance will not cover them.

Who is protected: Bradley County, TN residents

Legal detail

Suit by the owner of the ~306-acre Project MidSpan site (bought for ~$20M in April 2025) challenging Bradley County's recently approved data center zoning actions (3,000-ft school setback); seeks to enjoin enforcement. County Mayor Gary Davis told the County Commission on Monday Oct. 5, 2026 that insurance won't cover fees and the county will hire outside counsel from the general fund. NOT ESTABLISHED: court, case number, filing date, date of the zoning amendments (the underlying Bradley County data center zoning rules are not themselves in the dataset).

Key facts

JurisdictionBradley County, TN
LevelCounty
CitationBradley County, TN — Developer of 'Project MidSpan' Sues to Stop Enforcement of County Data Center Zoning Rules Requiring 3,000 Feet From Schools (October 2026)
Private right of actionNo, agency enforcement only
Topicsdata-center siting and energy
News reportBradley County faces self-funded legal costs in data center zoning lawsuit — WTVC NewsChannel 9 (Oct. 6, 2026)

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.