McMinnville, TN 18-Month Moratorium on Data Centers
McMinnville, TN · McMinnville, Tenn., data center moratorium (June 9, 2026; 18-month term)
McMinnville, Tennessee's Board of Mayor and Aldermen unanimously passed an 18-month moratorium on data center permitting on June 9, 2026, after more than 90 minutes of citizen comment. The moratorium gives the city time to evaluate impacts on the electrical grid, water and stormwater systems, environmental and public health, noise, and community fit. It was prompted by a developer's plan to build a 96,000-square-foot data center designed to support an Nvidia GB200 NVL72 AI supercomputing platform drawing 25 megawatts.
Technical detail
McMinnville Board of Mayor and Aldermen unanimous moratorium resolution (June 9, 2026; initial deliberations June 3, 2026) imposing an 18-month pause on data center permitting; triggered by a 96,000 sq ft / 25 MW Nvidia GB200 NVL72-focused AI data center proposal; studies to cover grid, water/stormwater, public health, noise, and zoning. Extendable if necessary.
Who is protected: McMinnville residents and utility ratepayers
Who must comply: Data center developers seeking permits in McMinnville
Key facts
| Jurisdiction | McMinnville, TN |
|---|---|
| Level | City / local |
| Status | In effect |
| Protection strength | Moderate protection |
| Effective date | 2026-06-09 |
| Enacted | 2026-06-09 |
| Citation | McMinnville, Tenn., data center moratorium (June 9, 2026; 18-month term) |
| Enforced by | City of McMinnville (planning/permitting) |
| Topics | data-center siting and energy |
| Last verified | 2026-06-16 |
| Official source | McMinnville approves 18-month moratorium on new data centers — WSMV ↗ |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.