Minneapolis Six-Month Interim Moratorium on Large Data Centers

Minneapolis, MN · Minneapolis, Minn., interim data center moratorium (May 22, 2026)

On May 22, 2026 the Minneapolis City Council voted 8–5 to impose a six-month moratorium on new large data centers while the city studies environmental and grid impacts and drafts zoning regulations. The pause targets facilities larger than 350,000 square feet and exempts smaller downtown developments — a size- and location-limited pause, not a total ban.

Technical detail

Minneapolis interim ordinance (May 22, 2026, 8–5) imposing a six-month moratorium on data center development over 350,000 sq ft, exempting downtown projects under that threshold, pending zoning study.

Who is protected: Minneapolis residents and ratepayers

Who must comply: Developers proposing large data centers in Minneapolis

Key facts

JurisdictionMinneapolis, MN
LevelCity / local
StatusEnacted (not yet in effect)
Protection strengthModerate protection
Enacted2026-05-22
CitationMinneapolis, Minn., interim data center moratorium (May 22, 2026)
Enforced byMinneapolis Community Planning & Economic Development (CPED)
Topicsdata-center siting and energy
Last verified2026-06-11
Official sourceMinneapolis City Council imposes six-month halt on data centers | MPR News ↗