Monroe County GA Data Center Moratorium
Monroe County, GA · Moratorium adopted December 2025 with built-in expiration at first March 2026 commission meeting (set as 2026-03-04 / first Tuesday)
In December 2025, the Monroe County (GA) Board of Commissioners passed a moratorium on new data-center applications. The moratorium was set to lapse at the first commission meeting in March 2026, at which point a new zoning ordinance was to be voted on; the action followed months of public debate over hyperscale data-center proposals in the county.
Technical detail
Moratorium adopted December 2025 with built-in expiration at first March 2026 commission meeting (set as 2026-03-04 / first Tuesday). Substantive zoning amendment to follow.
Who is protected: Monroe County, GA residents
Who must comply: Data-center developers and operators seeking permits, rezonings, or approvals in Monroe County, GA
Key facts
| Jurisdiction | Monroe County, GA |
|---|---|
| Level | County |
| Status | Expired |
| Protection strength | Moderate protection |
| Effective date | 2025-12-01 |
| Enacted | 2025-12-01 |
| Citation | Moratorium adopted December 2025 with built-in expiration at first March 2026 commission meeting (set as 2026-03-04 / first Tuesday) |
| Enforced by | Monroe County, GA government |
| Topics | data-center siting and energy |
| Last verified | 2026-06-17 |
| Official source | Monroe County passes data center moratorium (13 WMAZ) ↗ |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.