Jackson County NC one-year data center moratorium (2026-02)
Jackson County, NC — Ordinance 2026-02: One-Year Data Center Moratorium (August 18, 2026)
Jackson County, NC · Jackson Cnty., N.C. Ordinance 2026-02 (Aug. 18, 2026)
- Status
- In effect
- Expires
- August 18, 2027
- Applies to
- Anyone seeking county permits for data center development in Jackson County, NC; county planning and permitting staff.
- Enforced by
- Jackson County Planning Department / Board of Commissioners
The Jackson County Board of Commissioners approved Ordinance 2026-02 at its regular meeting on August 18, 2026, imposing a one-year moratorium on data center development. It took effect immediately and expires on August 18, 2027. During the pause the county will not issue permits for development connected to data centers as the ordinance defines them. The point of the year is definitional as much as protective: commissioners and the Planning Board intend to study what data centers would mean for the county, write a definition of 'data center' into the Unified Development Ordinance — which currently has none — and decide what regulations, if any, should follow. The ordinance is unusually even-handed in its own recitals, acknowledging that data centers may benefit the county's tax base while recording residents' concerns about how often the facilities are now being proposed and their effect on the quality of life of people living near them. Jackson County is in the mountains of far western North Carolina; its seat is Sylva.
Who is protected: Jackson County, North Carolina residents, through a one-year permit freeze while the county defines data centers in its Unified Development Ordinance and decides what regulation is warranted.
Legal detail
Jackson County, N.C. Ordinance 2026-02, adopted by the Board of Commissioners at its regular meeting August 18, 2026, effective immediately, expiring August 18, 2027. Suspends issuance of county permits for development related to data centers as defined in the moratorium. Stated purpose: to let the Board of Commissioners and the Planning Board study data center impacts, establish a definition of the use for the purposes of the county's Unified Development Ordinance (which did not previously define it), and potentially adopt regulations. Recitals expressly balance a possible tax-base benefit against residents' quality-of-life concerns and the rising frequency of proposals. DISAMBIGUATION — this dataset already carries two unrelated Jackson Counties: Jackson County FL data center ban (unincorporated, eff. June 23, 2026) (Jackson County, FLORIDA, effective 2026-06-23) and Jackson County MO 180-day data center + BESS moratorium (eff. June 22, 2026) (Jackson County, MISSOURI, effective 2026-06-22). This entry is Jackson County, NORTH CAROLINA and is a distinct jurisdiction and instrument from both. A triage note had provisionally guessed Tennessee on the strength of the outlet name; that was wrong.
Key facts
| Jurisdiction | Jackson County, NC |
|---|---|
| Level | County |
| Strength | Moderate |
| Enacted | August 18, 2026 |
| Citation | Jackson Cnty., N.C. Ordinance 2026-02 (Aug. 18, 2026) |
| Private right of action | No, agency enforcement only |
| Penalties | County permits for data-center-related development are not issued during the moratorium |
| Topics | data-center siting and energy · government use of AI |
| News report | Data center moratorium passes — The Sylva Herald |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.