Salem OR 120-day data center moratorium (Res. 2026-40)

Salem, Oregon — City Council Adopts a 120-Day Data Center Moratorium (Resolution No. 2026-40), Effective Sept. 21, 2026 Through Jan. 19, 2027
Salem, OR · City of Salem, Ore. — council vote initiating a temporary data center moratorium (August 3, 2026); DLCD 45-day notice due by August 10, 2026

Status
In effect
Expires
January 19, 2027
Applies to
Developers of primary-use data centers and of accessory data centers over 2 MW with PUE above 1.5 in Salem; the Verrus Oakline application continues to be processed but construction may be barred
Enforced by
City of Salem Community Development / Salem City Council; Oregon Department of Land Conservation and Development (notice)

Salem's City Council unanimously adopted a 120-day moratorium on data center construction and development on September 21, 2026 (Resolution No. 2026-40). It took effect immediately and runs to January 19, 2027 unless extended; Oregon law lets the city extend it up to six months after another hearing. It covers every data center that is a primary use, regardless of size, plus accessory data centers over 2 megawatts with a power usage effectiveness above 1.5. The city must keep processing Verrus's Oakline at Mill Creek application, filed before the moratorium, but construction can be barred while the pause lasts. The council started this process with a unanimous vote on August 3, 2026; a Data Center Task Force is due to report December 7.

Who is protected: Salem, Oregon residents and ratepayers — prospectively, if and when the moratorium takes effect

Legal detail

City of Salem, Ore. (Marion County) — City Council vote of August 3, 2026, taken unanimously at a SPECIAL MEETING after largely opposed public testimony, to BEGIN THE PROCESS for a temporary moratorium on data center applications. PROCEDURAL POSTURE — NOT IN EFFECT: Oregon land use law requires notice to the DEPARTMENT OF LAND CONSERVATION AND DEVELOPMENT (DLCD) in advance of a moratorium; city staff expected to send the 45-DAY NOTICE no later than August 10, 2026. Contemporaneous reporting stated expressly that no moratorium was then in effect. status is therefore `proposed` and effective_date is null. THE APPLICATION-TIMING PROBLEM: VERRUS, a California company, submitted its application for the OAKLINE AT MILL CREEK data center immediately before the council meeting. Reporting at the time held that the moratorium may not apply to it — Salem Business Journal: 'Salem Council Starts Data Center Moratorium, but the Vote May Not Reach the Project That Prompted It.' Under Oregon's goal-post rule (ORS 227.178), a complete application is generally reviewed under the standards in effect when it was submitted, which is the mechanism by which a pre-filed application survives a later moratorium — the same structural limit visible in Rockford IL six-month data center moratorium (2026), there arising from an annexation agreement rather than an application filing. STATE-LAND CONNECTION: Mill Creek Corporate Center is the site where Gov. Kotek blocked the sale of 32 acres of state land proposed for a data center (Oregon state-land data center transaction pause (2026)); reporting on 2026-08-01 described the data company advancing its Salem plan by REPLACING the state land in its proposal, i.e. routing around the state-level block. UNRESOLVED AS OF THIS ENTRY: Council was scheduled to receive moratorium updates on Monday, September 14, 2026 — one day before verification — and that outcome is not captured. [2026-10-01] ADOPTED: Resolution No. 2026-40, adopted unanimously Mon. Sept. 21, 2026 (7 in favor incl. Mayor Julie Hoy; Gwyn and Vang absent). Effective Sept. 21, 2026; expires Jan. 19, 2027 unless extended (date stated by Salem Business Journal; KPTV: 'until Jan. 19'). Extension up to six months permitted after additional public hearing and written findings; KPTV says council will consider extension in January. Scope: all data centers operating as a primary use regardless of size/capacity/purpose, plus accessory data centers >2 MW facility capacity with PUE >1.5. City Attorney Dan Atchison: pending Verrus Oakline at Mill Creek application must continue to be processed but construction/development can be prohibited during the moratorium. Data Center Task Force recommendations expected Dec. 7, 2026. The earlier 'NOT IN EFFECT / status proposed' text above describes the August 2026 posture and is superseded.

Key facts

JurisdictionSalem, OR
LevelCity / local
StrengthModerate
EnactedSeptember 21, 2026
CitationCity of Salem, Ore. — council vote initiating a temporary data center moratorium (August 3, 2026); DLCD 45-day notice due by August 10, 2026
Private right of actionNo, agency enforcement only
PenaltiesNot stated in the located sources
Topicsdata-center siting and energy · consumer protection · government use of AI
News reportUPDATED 10:11 p.m.: Salem City Council unanimously passes moratorium on data centers — Salem Reporter