Bethlehem, PA — Data Center Zoning Amendment (Special Exception in Industrial District, 1,000-Ft Residential Setback) Passes First Reading 7-0 (Oct. 6, 2026); Final Vote Set for Oct. 20
Bethlehem, PA · City of Bethlehem, PA, Zoning Ordinance Amendment: Data Centers (Bill No. __-2026), first reading Oct. 6, 2026
- Status
- Proposed / pending
- Applies to
- Data center developers in Bethlehem
- Enforced by
- City of Bethlehem Zoning Hearing Board; Department of Community and Economic Development
Bethlehem, Pennsylvania is close to adopting zoning rules for data centers. They would be allowed only by special exception in the Industrial district, at least 1,000 feet from homes, schools, day cares, parks and hospitals, and applicants would have to submit environmental, water, energy, sound, emergency and decommissioning studies up front. City Council approved the change 7-0 on first reading on Oct. 6, 2026, with a final vote set for Oct. 20.
Who is protected: Bethlehem, PA residents
Legal detail
Amends Part 13 (Zoning Ordinance) of the Bethlehem Codified Ordinances: adds a "Data Center" definition (new Art. 1302.35); permits data centers only as a Special Exception in the Industrial (IN) district (Zoning Hearing Board review); requires all plans, studies and mitigation strategies at application; 200-ft setback from any right-of-way or lot outside IN; 1,000-ft setback from any residential-district lot or lot with a sensitive receptor (dwelling, school, child/adult day care, park, hospital, community recreation center); max height, yards, buffer yards and building coverage limits scaled to building size; environmental assessment, water/sewer approvals, energy plan, emergency plan, decommissioning plan, heat and noise studies (post-occupancy noise study). Per Lehigh Daily, the pending Industrial Drive data center application predates the amendment and would not be subject to it.
Key facts
| Jurisdiction | Bethlehem, PA |
|---|---|
| Level | City / local |
| Citation | City of Bethlehem, PA, Zoning Ordinance Amendment: Data Centers (Bill No. __-2026), first reading Oct. 6, 2026 |
| Private right of action | No, agency enforcement only |
| Topics | data-center siting and energy |
| Agency page | City of Bethlehem — Director of Planning and Zoning memo and draft ordinance, Zoning Ordinance Amendment: Data Centers (July 15, 2026) |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.