East Whiteland Twp PA data center zoning Ord. 385-2026

East Whiteland Township, PA — Ordinance No. 385-2026 Permits Data Centers Only as a Conditional Use in the Industrial District, With Setbacks, Noise, Water, Power and Decommissioning Standards (September 2026)
East Whiteland Township, PA · East Whiteland Township, Chester County, PA — Ordinance No. 385-2026 (enacted Sept. 24, 2026), Zoning Ordinance Ch. 200 §§200-41, 200-43.1

Status
In effect
Took effect
September 24, 2026
Applies to
Applicants and operators of data centers in East Whiteland Township
Enforced by
East Whiteland Township Board of Supervisors (conditional use approval); township zoning/codes staff

East Whiteland Township's supervisors unanimously adopted a 32-page zoning ordinance for data centers. Data centers are now allowed only in the Industrial District and only as a conditional use, after the applicant shows with site-specific evidence that the facility will not harm the township's protected interests. The ordinance sets limits on how close a data center can be to homes, schools, daycares, parks and churches, and covers noise, water use, cooling systems, power supplies and emergency response. It does not apply to the large data center already under construction at the former Cyprus Foote Mineral site.

Who is protected: East Whiteland residents, schools, daycares, parks, churches and water resources near potential data center sites

Legal detail

Ordinance No. 385-2026, 'An Ordinance of East Whiteland Township, Amending East Whiteland Township Zoning Ordinance to Provide Regulations of Data Center and Related Uses' (32 pp.), enacted by the Board of Supervisors Sept. 24, 2026 (signed by Scott Lambert, Peter Fixler, Clinton Smith; attested by Township Manager Steve Brown); Section V: effective immediately upon adoption. Section I amends Chapter 200, §200-41 Table of Permitted Uses to add 'Data Center subject to Section 200-43.1' as a Conditional Use; Section II adds §200-43.1 Data Center Uses, permitting data centers only in the Industrial Zoning District under objective, performance-based standards — dimensional requirements, setbacks, noise and vibration limits, water-use restrictions, riparian buffers, emergency-response obligations, decommissioning security, financial security/escrow/mitigation funds — with applicants required to demonstrate through site-specific evidence verified by qualified consultants that there will be no adverse effects. Findings cite groundwater/stream baseflow, low-frequency noise, grid reliability (public safety priority over high-density users), BESS thermal runaway and fuel storage hazards. Inquirer: unanimous vote after months of a data center moratorium; does not affect the 1.5M sq ft project at the former 79-acre Cyprus Foote Mineral Co. property; chairman Lambert called it amendable. Township page lists a curative amendment timeline and a Chester County review letter (CA-08-26-19068). NOT ESTABLISHED here: specific setback distances and decibel limits (not read from the scanned pages beyond pp. 1-2 and 32).

Key facts

JurisdictionEast Whiteland Township, PA
LevelCity / local
StrengthModerate
EnactedSeptember 24, 2026
CitationEast Whiteland Township, Chester County, PA — Ordinance No. 385-2026 (enacted Sept. 24, 2026), Zoning Ordinance Ch. 200 §§200-41, 200-43.1
Private right of actionNo, agency enforcement only
PenaltiesNot stated in the located sources
Topicsdata-center siting and energy
Agency pageSentinel, Green Fig Data Center on Swedesford Road — East Whiteland Township (documents incl. Enacted Ordinance No. 385-2026)

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.