Gregg Township PA data center moratorium resolution (2026)

Gregg Township, Pennsylvania — Board of Supervisors Passes a Resolution Establishing a Moratorium on New Data Center Development, Temporarily Barring the ACCEPTANCE and PROCESSING of Applications (2026)
Gregg Township, PA · Gregg Township, Pa. — resolution establishing a moratorium on new data center development (2026)

Status
In effect
Took effect
September 1, 2026
Applies to
Parties seeking to file or advance data center applications in Gregg Township
Enforced by
Gregg Township Board of Supervisors

The Gregg Township Board of Supervisors passed a RESOLUTION establishing a moratorium on new data center development, temporarily barring the ACCEPTANCE and PROCESSING of applications. Barring acceptance is the stronger half of that pair and the one most often omitted elsewhere: an application that cannot be filed cannot begin to accrue the rights that defeat a pause later. This dataset records what happens when that step is missing — in Inver Grove Heights, Minnesota a filed application became a $150 million damages demand that forced the city to amend its ordinance to let the project through. Gregg Township is in Union County, and the dateline on the reporting is Allenwood. Note the instrument is a RESOLUTION rather than a zoning ordinance amendment, which in Pennsylvania is a meaningful distinction — the Municipalities Planning Code governs how zoning is enacted and amended, and a resolution directing staff not to accept applications is a weaker footing than an enacted interim ordinance if a developer chooses to test it.

Who is protected: Gregg Township residents in Union County, Pennsylvania

Legal detail

Gregg Township, Pa. (Union County; Allenwood dateline) — RESOLUTION ESTABLISHING A MORATORIUM on new data center development passed by the BOARD OF SUPERVISORS on a Thursday in 2026, 'temporarily barring the acceptance, processing a[nd approval]' of applications (the captured sentence is truncated). OPERATIVE SCOPE: acceptance AND processing, with approval implied by the truncation but NOT established. BARRING ACCEPTANCE IS THE OPERATIVE PROTECTION: an unfiled application cannot ripen, which forecloses the vested-rights exposure recorded at Rockford IL (annexation agreement), Cle Elum WA (2002 development agreement), Salem (pre-filed application), Lowell (settlement) and most acutely Inver Grove Heights MN data center moratorium amended under lawsuit (2026) (a filed application became a $150M damages demand and the city amended its ordinance rather than litigate). Compare the three-verb formulations at Marysville KS 12-month data center moratorium (2026), McDonald OH one-year data center moratorium (2026) and Arcata CA 45-day data center moratorium (2026). INSTRUMENT CAUTION: the measure is a RESOLUTION, not an enacted interim zoning ordinance. Under the Pennsylvania Municipalities Planning Code zoning is enacted and amended by ordinance following prescribed notice and hearing; A RESOLUTION DIRECTING THAT APPLICATIONS NOT BE ACCEPTED IS A WEAKER FOOTING if tested, and is closer in form to West Mahanoy Township PA curative amendment, data centers and solar (2026) (also a resolution, but one invoking the MPC curative amendment procedure and thereby securing a statutory 180-day shield) than to an interim ordinance. WHETHER GREGG TOWNSHIP INVOKED THE CURATIVE AMENDMENT PROCEDURE IS NOT ESTABLISHED and would materially affect durability. NOT ESTABLISHED: THE TERM LENGTH (not reported; expires_date left NULL), the vote, the exact date, the resolution number, and any threshold.

Key facts

JurisdictionGregg Township, PA
LevelCity / local
StrengthModerate
EnactedSeptember 1, 2026
CitationGregg Township, Pa. — resolution establishing a moratorium on new data center development (2026)
Private right of actionNo, agency enforcement only
PenaltiesNot stated in the located source
Topicsdata-center siting and energy · consumer protection · government use of AI
News reportGregg Township passes data center moratorium — The Standard-Journal (Milton, PA)

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.