West Hempfield Twp PA data center zoning ordinance (2026)
West Hempfield Township (Lancaster County), PA — Supervisors Unanimously Adopt Data Center Ordinance: Conditional Use in General Industrial Zone, 120,000 Sq Ft Cap, 1,000-Foot Buffer From Homes and Farm Buildings (September 2026)
West Hempfield Township, PA · West Hempfield Township (Lancaster County), PA — data center zoning ordinance
- Status
- Enacted (not yet in effect)
- Applies to
- Data center developers in West Hempfield Township
- Enforced by
- West Hempfield Township Board of Supervisors; zoning officer / zoning hearing board
West Hempfield Township's supervisors unanimously approved an ordinance regulating where and how big data centers can be. Data centers are allowed only in the general industrial district with conditional use approval from the supervisors, are capped at 120,000 square feet (156,000 if 75% has a green roof) and 75 feet tall, and must be at least 1,000 feet from homes and farm buildings. Sound studies and water-saving technology such as closed-loop cooling are required. A developer has inquired about the district but no plans have been submitted; the planning commission will consider further amendments on noise, water use and decommissioning.
Who is protected: Residents of West Hempfield Township, Lancaster County, PA
Legal detail
West Hempfield Township, Lancaster County, Pennsylvania — Board of Supervisors UNANIMOUS adoption of a land-use ordinance governing data centers following a public hearing. DATE: WGAL (published Sept. 1, 2026, 10:13 p.m. ET) says 'Monday night' (Aug. 31); LNP's meeting brief says 'Board of Supervisors meeting, Sept. 1'; the roundup says 'voted in September'. enacted_date left null because of this conflict. PROVISIONS (LNP): conditional use approval by the supervisors in the GENERAL INDUSTRIAL district; buildings max 120,000 sq ft (156,000 sq ft if 75% green roof); 75 ft height; restrictions on sound, light and noise; 1,000 ft from the nearest residential property line or agricultural building (Township Manager Andrew Stern: among the most restrictive in Pennsylvania); sound studies; water conservation technology such as closed-loop cooling; groundwater feasibility study. FUTURE: planning commission to consider amendments on noise, water use and decommissioning (WGAL). A developer has inquired about the general industrial district but no plans have been submitted (LNP roundup). CONTEXT (same roundup): Pennsylvania's Municipalities Planning Code gives municipalities zoning authority but state law prohibits outright bans of a legitimate land use; Lancaster County Planning Commission issued a guide for municipal data center rules.
Key facts
| Jurisdiction | West Hempfield Township, PA |
|---|---|
| Level | City / local |
| Strength | Moderate |
| Citation | West Hempfield Township (Lancaster County), PA — data center zoning ordinance |
| Private right of action | No, agency enforcement only |
| Penalties | Not stated in the located sources |
| Topics | data-center siting and energy |
| News report | West Hempfield supervisors adopt data center safeguards after residents raise concerns — WGAL |
Related data-center siting and energy rules elsewhere
- Superior WI Data Center Moratorium (1-year) · In effect
- Dane County WI Hyperscale Data Center Moratorium · In effect
- Madison WI Data Center Moratorium (1-year) · In effect
- Manitowoc County WI Data Center Moratorium · In effect
- WA SB 5982 (Data Center / Clean Energy) · In effect
- Dayton OH data center moratorium (180-day, Apr 2026) · In effect
See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.