Pasco County FL 1-year data center moratorium (eff. July 14, 2026)

Pasco County, FL 1-Year Moratorium on Large Data Centers (>2.5MW)
Pasco County, FL · Pasco County, FL Board of County Commissioners action, July 14, 2026, 1-year moratorium on data centers >2.5MW

Status
In effect
Expires
July 14, 2027
Applies to
Developers of data centers >2.5MW seeking approvals in Pasco County, FL
Enforced by
Pasco County, FL Planning and Development; Board of County Commissioners

Pasco County, Florida (north of Tampa) adopted a one-year moratorium on July 14, 2026 covering large data centers — those that would use more than 2.5 megawatts of power. The county will use the year to develop regulations for data center siting.

Who is protected: Pasco County, FL residents

Legal detail

Pasco County (FL) Board of County Commissioners action July 14, 2026: 12-month moratorium on data centers exceeding a 2.5MW power threshold (through approximately July 14, 2027). Notably low MW threshold compared to peer Florida counties (Sarasota's is 50MW), giving the pause broad practical scope.

Key facts

JurisdictionPasco County, FL
LevelCounty
StrengthModerate
EnactedJuly 14, 2026
CitationPasco County, FL Board of County Commissioners action, July 14, 2026, 1-year moratorium on data centers >2.5MW
PenaltiesPermit/application denial during moratorium
Topicsdata-center siting and energy
News reportPasco County adopts one-year moratorium on large data centers — WUSF

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.