Pocatello ID data center CUP denial upheld (July 16, 2026)

Pocatello, ID Denial of Conditional Use Permit for 100MW Lex Developments AI Data Center
Pocatello, ID · Pocatello, ID City Council 4-1 vote, July 16, 2026, upholding CUP denial for Lex Developments 100MW AI data center

Status
In effect
Took effect
July 16, 2026
Applies to
Lex Developments (12-month reapplication bar); future data center CUP applicants in Pocatello, ID
Enforced by
City of Pocatello, ID Planning and Development Services; City Council

Pocatello, Idaho's city council said no to a proposed $2.6 billion AI data center. On July 16, 2026 the council voted 4-1 to uphold a hearing examiner's earlier denial of the conditional use permit for the 100-megawatt Lex Developments project. The developer cannot reapply for 12 months and has vowed to sue. The Shoshone-Bannock Tribes were among the project's opponents.

Who is protected: Pocatello, ID residents; Shoshone-Bannock Tribes (project opponents)

Legal detail

Pocatello (ID) City Council 4-1 vote July 16, 2026 upholding the hearing examiner's denial of a conditional use permit (CUP) for Lex Developments' proposed AI data center ($2.6B capital, 100MW). Effect: CUP denied; 12-month bar on reapplication. Developer has stated intent to litigate — watch for a suit that would add a litigation entry. Opposition included the Shoshone-Bannock Tribes.

Key facts

JurisdictionPocatello, ID
LevelCity / local
StrengthModerate
EnactedJuly 16, 2026
CitationPocatello, ID City Council 4-1 vote, July 16, 2026, upholding CUP denial for Lex Developments 100MW AI data center
PenaltiesCUP denial; 12-month reapplication bar
Topicsdata-center siting and energy
News reportPocatello City Council upholds hearing examiner's decision, says no to proposed AI data center — Local News 8