Spotsylvania County VA Data Center Design Standards

Spotsylvania County VA Data Center Design Standards (Industrial Districts)
Spotsylvania County, VA · Design standards adopted 2025-12-09 after the SUP motion failed at both the 2025-03-25 and 2025-08-13 sessions

Status
In effect
Took effect
December 9, 2025
Applies to
Data-center developers and operators seeking permits, rezonings, or approvals in Spotsylvania County, VA
Enforced by
Spotsylvania County, VA government

On December 9, 2025, the Spotsylvania County Board of Supervisors approved design standards for data centers in industrial districts, after the Board deadlocked 3-3 in March 2025 on a stronger special-use permit requirement and a 4-3 August 2025 vote declined to require SUPs. The December standards govern data-center building design in industrial zones without imposing the SUP gate that supervisors split on earlier in the year.

Who is protected: Spotsylvania County, VA residents

Legal detail

Design standards adopted 2025-12-09 after the SUP motion failed at both the 2025-03-25 and 2025-08-13 sessions. Spotsylvania remains a 'data centers by-right in industrial' jurisdiction with design-only conditions.

Key facts

JurisdictionSpotsylvania County, VA
LevelCounty
StrengthLimited
EnactedDecember 9, 2025
CitationDesign standards adopted 2025-12-09 after the SUP motion failed at both the 2025-03-25 and 2025-08-13 sessions
Topicsdata-center siting and energy
Agency pageSpotsylvania County, VA — Code Amendments

More AI rules in Spotsylvania County, VA

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.