Story County IA Data Center Moratorium (Resolution #25-97)

Story County IA Data Center Moratorium (Resolution #25-97, Expired Dec 2025)
Story County, IA · Initial moratorium 2025-06-17 (expires ≤2025-12-31)

Status
Expired
Expired
December 31, 2025
Applies to
Data-center developers and operators seeking permits, rezonings, or approvals in Story County, IA
Enforced by
Story County, IA government

On June 17, 2025, Story County (IA) imposed a temporary moratorium on data-center development in unincorporated areas, with an expiration on or before December 31, 2025. On November 25, 2025, the County Board of Supervisors authorized a one-time extension. The moratorium expired December 31, 2025. On March 17, 2026, the Board adopted Ordinance 330 (case TA26-000002), which covers battery-energy storage systems (BESS) only — the Board expressly removed proposed supplemental data-center standards during deliberations. No permanent data-center ordinance was adopted to replace the moratorium.

Who is protected: Story County, IA residents

Legal detail

Initial moratorium 2025-06-17 (Resolution #25-97, expires ≤2025-12-31). Extension 2025-11-25. Ordinance 330 (case TA26-000002) adopted March 17, 2026 — covers BESS only; data-center provisions expressly removed by Board. Moratorium expired 2025-12-31. No permanent data-center ordinance enacted.

Key facts

JurisdictionStory County, IA
LevelCounty
EnactedJune 17, 2025
CitationInitial moratorium 2025-06-17 (expires ≤2025-12-31)
Topicsdata-center siting and energy
Agency pageStory County Planning and Development — agenda item (Ordinance 330 / TA26-000002)

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.