Tucson UDC Amendment: Large-Scale Data Center Zoning Regulations (adopted August 5, 2026)

Tucson, AZ · City of Tucson, UDC Text Amendment (adopted August 5, 2026, 6-1 vote)

Tucson's City Council voted 6-1 on August 5, 2026 to adopt citywide zoning rules for large data centers. Projects over 25,000 square feet or 20 megawatts must obtain Planned Area Development zoning, allowing the Mayor and Council to review each project, and must meet setback, noise, habitat, and grid-protection standards. The ordinance makes Tucson one of the first Arizona cities to establish permanent data center siting regulations.

Technical detail

Unified Development Code text amendment adopted August 5, 2026 (6-1 vote). Requires Planned Area Development (PAD) or Planned Community Development (PCD) zoning for data centers >25,000 sq ft or >20 MW demand; residential setback requirements; property-line noise limits; sound walls; battery-first backup power; and habitat preservation standards. City of Tucson Mayor and Council retain review authority over each qualifying data center project.

Who is protected: Tucson residents and neighborhoods near proposed large data center sites

Who must comply: Developers and operators of large-scale data centers in Tucson

Key facts

JurisdictionTucson, AZ
LevelCity / local
StatusIn effect
Protection strengthModerate protection
Effective date2026-08-05
Enacted2026-08-05
CitationCity of Tucson, UDC Text Amendment (adopted August 5, 2026, 6-1 vote)
Enforced byCity of Tucson Planning and Development Services; Mayor and Council
Topicsdata-center siting and energy
Last verified2026-08-09
Official sourceLarge-Scale Data Center Zoning Regulations — City of Tucson Planning Initiatives (adopted Aug. 5, 2026) ↗