New GS-5 Data Center / Large Load Rate Class, DEV 2025 Biennial Review…

Virginia State Corporation Commission (Dominion Energy Virginia) — New GS-5 Data Center / Large Load Rate Class, DEV 2025 Biennial Review (Case PUR-2025-00058)
Virginia State Corporation Commission (Dominion Energy Virginia) · New GS-5 Data Center / Large Load Rate Class, DEV 2025 Biennial Review (Case PUR-2025-00058)

Status
In effect
Took effect
November 25, 2025
Applies to
Virginia State Corporation Commission (Dominion Energy Virginia)

The Virginia SCC created a new GS-5 rate class (effective Jan 1, 2027) for customers exceeding 25 MW with load factor above 75%, requiring 14-year contracts and minimum demand charges of 85% for transmission/distribution and 60% for generation so data centers pay their own costs.

Who is protected: People subject to this body's AI/surveillance systems.

Key facts

JurisdictionVirginia State Corporation Commission (Dominion Energy Virginia)
LevelState
StrengthLimited
CitationNew GS-5 Data Center / Large Load Rate Class, DEV 2025 Biennial Review (Case PUR-2025-00058)
Topicsdata-center siting and energy · consumer protection · government use of AI
News reportVirginia regulators approve new rate class for data centers and other large loads | DCD