Town of Warrenton VA Zoning Ordinance Amendment

Town of Warrenton VA Zoning Ordinance Amendment — Data Centers Removed from Industrial Use
Warrenton, VA · Town zoning ordinance amendment 2025-07-08 fully removes data-center use category from town industrial districts

Status
In effect
Took effect
July 8, 2025
Applies to
Data-center developers and operators seeking permits, rezonings, or approvals in Warrenton, VA
Enforced by
Warrenton, VA government

On July 8, 2025, the Warrenton Town Council amended its zoning ordinance to remove data centers as a permissible use in industrial zoning districts within town limits. Warrenton is the county seat of Fauquier County and the action is parallel to Fauquier County's 2024 Vint Hill PCID restrictions on data centers above 50,000 sq ft.

Who is protected: Warrenton, VA residents

Legal detail

Town zoning ordinance amendment 2025-07-08 fully removes data-center use category from town industrial districts.

Key facts

JurisdictionWarrenton, VA
LevelCity / local
StrengthStronger
EnactedJuly 8, 2025
CitationTown zoning ordinance amendment 2025-07-08 fully removes data-center use category from town industrial districts
Topicsdata-center siting and energy
Agency pageWarrenton Town Council pushes back against data centers, amends zoning ordinance (Fauquier Now)

More AI rules in Warrenton, VA

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.