Howard County IN one-year data center moratorium (2026-BCCO-32)

Howard County, IN — Commissioners Adopt One-Year Moratorium on Data Center Permit Applications in Unincorporated Areas (Ordinance 2026-BCCO-32, Aug. 17, 2026)
Howard County, IN · Howard County, IN Ordinance 2026-BCCO-32 (adopted Aug. 17, 2026)

Status
In effect
Took effect
August 17, 2026
Applies to
Data center developers in unincorporated Howard County
Enforced by
Howard County Board of Commissioners / Plan Commission

Howard County, Indiana stopped accepting permit applications for new data centers in unincorporated parts of the county for one year while officials write rules for them. It does not cover Kokomo or other towns. It may end early if permanent rules are finished, or be extended.

Who is protected: Unincorporated Howard County, IN residents

Legal detail

Howard County, IN Board of Commissioners, Ordinance 2026-BCCO-32, approved Mon. 2026-08-17 (Kokomo Tribune, Aug. 18). Temporarily prevents companies from applying for or obtaining permits to develop data centers in unincorporated Howard County for one year (~2027-08-17, computed); may end early on adoption of permanent regulations or be extended. County Attorney Alan Wilson: data centers may need oversight beyond existing zoning. Excludes Kokomo and other incorporated communities (see Kokomo IN data center zoning standards (2026)). Vote tally not reported.

Key facts

JurisdictionHoward County, IN
LevelCounty
StrengthModerate
EnactedAugust 17, 2026
CitationHoward County, IN Ordinance 2026-BCCO-32 (adopted Aug. 17, 2026)
Private right of actionNo, agency enforcement only
PenaltiesPermit applications not accepted during the moratorium
Topicsdata-center siting and energy · government use of AI
News reportHoward County approves one-year moratorium on data center permits — Kokomo Tribune (Aug. 18, 2026)

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.