Imperial County CA CEQA ruling, 330 MW data center EIR (2026)

Imperial County, California — Superior Court Orders a Full Environmental Impact Report for a 330 MW Data Center, Holding the County Wrongly Treated Approvals as Ministerial and Cannot Review 132 Gas Generators, a Substation and 862 MWh of Batteries Piecemeal (September 1, 2026)
Imperial County, CA · Imperial County Superior Court (Cal.) — tentative ruling requiring a full EIR for the Imperial Valley Computer Manufacturing 330 MW data center (September 1, 2026) (Anderholt, J.)

Status
Blocked / in litigation
Applies to
Imperial County, which must prepare a full Environmental Impact Report before approving the project; Imperial Valley Computer Manufacturing, LLC, barred from grading, construction or physical development pending review
Enforced by
Imperial County Superior Court (Judge L. Brooks Anderholt); Imperial County as CEQA lead agency

Judge L. Brooks Anderholt of the Imperial County Superior Court issued a tentative ruling on September 1, 2026 holding that Imperial County must conduct a FULL ENVIRONMENTAL IMPACT REPORT under the California Environmental Quality Act before approving Imperial Valley Computer Manufacturing LLC's 330-megawatt data center, on roughly 75 acres southeast of Aten Road and Clark Road. The ruling identifies two distinct failures. First, the county improperly treated its approvals as MINISTERIAL — meaning a rubber-stamp determination that the application met fixed standards, which under CEQA carries no environmental review obligation at all. The court held the approvals were not ministerial, which restores the review duty. Second, the county relied on a 2017 ENVIRONMENTAL REVIEW that did not address the current proposal. Nine-year-old analysis of a different project cannot substitute for analysis of this one. The most useful part of the ruling is its treatment of scope. The court found the project encompasses INTEGRATED INFRASTRUCTURE that must be evaluated comprehensively rather than piecemeal: a 330 MW substation, an 862 MWh battery storage system, emergency generation comprising 132 NATURAL GAS GENERATORS, and water treatment facilities. Splitting a data center from its substation, its batteries and its generator farm — and reviewing each as if it were a separate small project — is the standard way large facilities avoid full environmental review, and this ruling forecloses it. The tentative decision prevents grading, construction and physical development from proceeding until proper review occurs. It is a tentative ruling, and no final judgment or appeal is reflected in the located source.

Who is protected: Imperial County residents near the Aten Road and Clark Road site; regional air quality and water resources in a CEQA environmental justice context

Legal detail

Imperial County Superior Court (Cal.) — TENTATIVE RULING of JUDGE L. BROOKS ANDERHOLT dated SEPTEMBER 1, 2026 concerning IMPERIAL VALLEY COMPUTER MANUFACTURING, LLC's 330 MW data center on approximately 75 ACRES southeast of ATEN ROAD and CLARK ROAD, Imperial County, California. GOVERNING LAW: CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA). HOLDINGS: (1) THE COUNTY IMPROPERLY TREATED ITS APPROVALS AS 'MINISTERIAL'. Ministerial approvals are exempt from CEQA review because they involve no exercise of judgment; characterising a discretionary approval as ministerial removes the environmental review obligation entirely, and is the single most consequential classification decision in California land use. The court rejected that characterisation. (2) THE COUNTY RELIED ON A 2017 ENVIRONMENTAL REVIEW THAT DID NOT ADDRESS THE CURRENT PROPOSAL \u2014 nine-year-old analysis of different facts cannot serve as the review for this project. (3) ANTI-PIECEMEALING: the project encompasses INTEGRATED INFRASTRUCTURE that must be evaluated COMPREHENSIVELY RATHER THAN PIECEMEAL, specifically a 330 MW SUBSTATION, an 862 MWh BATTERY STORAGE SYSTEM, EMERGENCY GENERATION COMPRISING 132 NATURAL GAS GENERATORS, and WATER TREATMENT FACILITIES. THE ANTI-PIECEMEALING HOLDING IS THE TRANSFERABLE ONE: segmenting a hyperscale facility from its substation, storage and on-site generation, and reviewing each component as a separate minor project, is the standard route by which large data centers avoid a full EIR. A court identifying the substation, the 862 MWh of batteries and 132 gas generators as one project with the data center closes that route in California. THE 132 NATURAL GAS GENERATORS ARE WORTH NOTING INDEPENDENTLY: on-site combustion at that scale is an air quality question of a different order from the diesel backup at issue in Lowell MA Markley data center diesel generator injunction (2026), where a Massachusetts court enjoined FOUR generators. RELIEF: the tentative decision PREVENTS GRADING, CONSTRUCTION OR PHYSICAL DEVELOPMENT from proceeding until proper environmental review occurs, and requires a full EIR before approval. STATUS: TENTATIVE ruling; no final judgment or appellate action is reflected in the located source. Imperial County separately has indexed data center measures (Imperial CA Data Center Moratorium, Imperial County Data Center Moratorium (45-day, adopted June 16, 2026), Calipatria CA Data Center Moratorium (introduced)).

Key facts

JurisdictionImperial County, CA
LevelCounty
CitationImperial County Superior Court (Cal.) — tentative ruling requiring a full EIR for the Imperial Valley Computer Manufacturing 330 MW data center (September 1, 2026) (Anderholt, J.)
Private right of actionYes, individuals can sue
PenaltiesGrading, construction and physical development are prevented until a full EIR is completed
Topicsdata-center siting and energy · government use of AI · consumer protection · AI disclosure and transparency
News reportCalifornia Judge Orders Full Environmental Review of 330 MW Data Center — Data Center Knowledge