Texas SB 6 (Data Center Grid Law)

Texas SB 6 (2025): Large Load Interconnection and Curtailment in ERCOT (data centers)
Texas · Tex. SB 6 (2025), amending Tex. Util. Code

Status
In effect
Took effect
June 21, 2025
Applies to
Large-load customers (>75 MW) including data centers and crypto miners; transmission providers and utilities
Enforced by
Public Utility Commission of Texas; ERCOT

Texas now regulates how very large electricity users such as data centers connect to the ERCOT grid. Loads over 75 MW face a minimum $100,000 transmission study fee and financial commitments, and new large loads must install remote-disconnect capability so ERCOT can curtail them during grid emergencies.

Who is protected: ERCOT ratepayers and grid reliability generally

Legal detail

SB 6 (89th Leg.) amends the Utilities Code to require PUCT interconnection standards for large loads (default 75 MW threshold), mandatory curtailment protocols for post-2025 interconnections during firm load shed, and uniform cost-allocation/transmission screening fees.

Key facts

JurisdictionTexas
LevelState
StrengthLimited
EnactedJune 20, 2025
CitationTex. SB 6 (2025), amending Tex. Util. Code
Private right of actionNo, agency enforcement only
PenaltiesCurtailment/disconnection authority; interconnection denial; fees and financial commitments
Topicsdata-center siting and energy · consumer protection
Bill textTexas Legislature Online: SB 6 (89R)