Bellevue WI 12-month data center moratorium (2026)

Bellevue, Wisconsin — Village Board Unanimously Adopts a 12-Month Data Center Moratorium by Zoning Code Amendment, With the Administrator Stating Wisconsin Law Caps Moratoriums at 12 Months Plus One Six-Month Extension (August 12, 2026)
Bellevue, WI · Village of Bellevue, Wis. — 12-month data center moratorium by amendment to Zoning Code ch. 500 (adopted August 12, 2026)

Status
In effect
Expires
August 12, 2027
Applies to
Developers seeking to develop or construct data centers in Bellevue during the 12-month moratorium
Enforced by
Village of Bellevue zoning administration / Bellevue Village Board

The Bellevue Village Board held a public hearing and unanimously passed a temporary TWELVE-MONTH moratorium on data centers on Wednesday, August 12, 2026, expiring in August 2027. It was done as an AMENDMENT TO CHAPTER 500 of the village Zoning Code — not as a standalone resolution — which is the more durable route, the same choice Garfield Township Michigan made deliberately for legal defensibility. The board also adopted a definition, which many jurisdictions omit and later regret: a data center is 'a dedicated building, facility or campus used primarily to house computer system servers that process, store and transmit digital data.' The most valuable thing in this record is what Village Administrator Benjamin Krumenauer told the board before the hearing. He explained that THE STATE OF WISCONSIN'S REGULATIONS LIMIT THE LENGTH of a moratorium and how far it can be amended: 'Wisconsin allows for up to 12 months and one additional six month extension — if appropriate — at which point in time the board would correct whatever perceived issue they have in their code... or the moratorium would simply expire.' And he added the principle behind it: 'Moratoriums are not meant to be a tool to prohibit something forever.' That is a STATUTORY CEILING of eighteen months in Wisconsin, stated on the record by a village administrator — which independently corroborates the twelve-to-eighteen-month defensibility estimate Henderson Nevada's city attorney gave, and raises a direct question about the Wisconsin entries in this dataset that run to eighteen months.

Who is protected: Village of Bellevue residents in Brown County, Wisconsin

Legal detail

Village of Bellevue, Wis. (Brown County) — temporary 12-MONTH data center moratorium, adopted UNANIMOUSLY by the Village Board following a public hearing on WEDNESDAY, AUGUST 12, 2026, expiring AUGUST 2027. INSTRUMENT FORM: an AMENDMENT TO CHAPTER 500 OF THE BELLEVUE ZONING CODE, temporarily blocking the development or construction of data centers \u2014 not a freestanding resolution. This is the same durability-motivated choice recorded on Garfield Township MI data center and crypto mining ban (2026), where officials said municipalities enacting standalone 'knee-jerk moratoriums' 'are being challenged and losing in court'. ADOPTED DEFINITION, which many jurisdictions in this dataset omitted and had to add later: a data center is 'a dedicated building, facility or campus used primarily to house computer system servers that process, store and transmit digital data.' THE STATUTORY CEILING IS THE MOST IMPORTANT CONTENT HERE. Village Administrator BENJAMIN KRUMENAUER stated on the record that 'The state of Wisconsin's regulations limit the length and overall time you can amend the length of a moratorium' and that 'Wisconsin allows for up to 12 months and one additional six month extension \u2014 if appropriate \u2014 at which point in time the board would correct whatever perceived issue they have in their code... or the moratorium would simply expire', adding that 'Moratoriums are not meant to be a tool to prohibit something forever.' AN 18-MONTH STATUTORY MAXIMUM IN WISCONSIN, stated by a municipal administrator, has direct consequences for other Wisconsin entries in this dataset: Cottage Grove WI 18-month data center moratorium (2026) was adopted at EIGHTEEN MONTHS in a single step, which on Krumenauer's account would exhaust the entire statutory allowance at once and leave no extension available; Chippewa County WI 12-month data center moratorium (2026) (12 months) and Town of Janesville WI data center moratorium (2026) (12 months) sit within the base allowance. It also independently corroborates, from a statutory rather than litigation-risk direction, the 12-to-18-month figure given by Henderson, Nevada's city attorney (Henderson NV rejects data center moratorium, pursues code changes (2026)). THIS IS AN ADMINISTRATOR'S CHARACTERISATION OF STATE LAW, NOT A CITATION \u2014 the underlying Wisconsin statute is not named in the source and should be identified before the ceiling is treated as settled.

Key facts

JurisdictionBellevue, WI
LevelCity / local
StrengthModerate
EnactedAugust 12, 2026
CitationVillage of Bellevue, Wis. — 12-month data center moratorium by amendment to Zoning Code ch. 500 (adopted August 12, 2026)
Private right of actionNo, agency enforcement only
PenaltiesDevelopment or construction of data centers is temporarily blocked under the amended Zoning Code chapter 500
Topicsdata-center siting and energy · consumer protection · government use of AI
News reportBellevue Village Board passes data center moratorium — Green Bay Press Times

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction. Every entry must carry a verifiable source.